KUALA LUMPUR, Feb 4 — Malaysia Airports Holdings Bhd (MAHB) has yet to receive the Certificate of Completion and Compliance (CCC) for the KLIA2 terminal building from UEMC-Bina Puri joint-venture (JV), which was scheduled on January 31, 2014.

In a filing to Bursa Malaysia today, MAHB said it would continue to engage with UEMC-Bina Puri JV on the next course of action in regard to the issuance of the CCC and the commencement of Operational Readiness and Airport Transfer.

“All efforts are being taken to support UEMC-Bina Puri JV towards the completion of the terminal building to enable the opening of KLIA2 on May 2, 2014,” it said. — Bernama