KUALA LUMPUR, Nov 25 — The government, through the Selangor Department of Irrigation and Drainage (DID), is implementing three immediate mitigation measures to reduce flood risks in Shah Alam, with construction work expected to be completed between February and March next year.
Deputy Minister of Energy Transition and Water Transformation Datuk Seri Abdul Rahman Mohamad said the first project involves the construction of a flood wall and the installation of a flap gate at Taman Rashna, at a cost of RM350,000, with completion scheduled for March 17, 2027.
The second project entails the construction of an outlet structure, the installation of a flap gate, and the building of a flood wall near the Bukit Raja junction, at a cost of RM199,000, with completion scheduled for Feb 17, 2027.
“Third, there is the construction of a flood wall at Taman Intan, costing RM200,000, which is also scheduled for completion on Feb 17, 2027,” he said during a Special Chamber session in the Dewan Rakyat today.
He was responding to a question from Azli Yusof (PH-Shah Alam) regarding the status of flood control plans for the Sungai Rasah Basin, following recent flash flood incidents.
Abdul Rahman added that DID has also deployed six mobile pump units across four high-risk locations namely Taman Rashna, Taman Intan, the area near the Bukit Raja junction, and the AEON supermarket to accelerate the drainage of floodwaters, thereby reducing the duration of water stagnation.
For the long term, he said the government has approved an allocation of RM40 million under the First Rolling Plan of the 13th Malaysia Plan (13MP) for the construction of a water control gate at the estuary of the Sungai Rasah, as well as a pump house, a flood retention basin, and riverbank retaining walls.
“The project is currently in the preliminary design stage, with physical works targeted to commence in the second quarter of 2028 and expected to be completed by 2031,” he said.
Abdul Rahman noted that the ministry has also proposed splitting the RM40 million allocation into two separate tenders to accelerate the project’s implementation, potentially shortening the construction period to 2029, ahead of the original 2031 target.
He explained that a key focus will be preventing water from the Sungai Klang from overflowing into high-risk areas in Shah Alam and this component is estimated to cost between RM15 million and RM20 million, depending on the final scope and the findings of technical studies.
“Overall, the planning for these components aims to enhance the capacity of the flood control system in the Sungai Rasah Basin, making it more integrated and effective.
“These measures are expected to reduce the risk and impact of flooding on residents and the surrounding areas; however, the final scope of the project remains subject to the results of studies and detailed designs prepared by the consultants,” he said. — Bernama