Malaysia
KLIA Runway 3 resumes full operations seven days ahead of schedule
Tuesday, 10 Mar 2026 5:38 PM MYT
KUALA LUMPUR, March 10 — Kuala Lumpur International Airport’s (KLIA) Runway 3 has resumed full operations seven days ahead of schedule.
KLIA said improvement works began with a full closure from February 24-26, followed by operations under a shortened runway configuration while the remaining works progressed.
“With the works now completed earlier than planned, the runway has resumed full-length operations ahead of schedule,” it said in an official X posting.
It added that the works form part of KLIA’s ongoing efforts to maintain the highest safety and quality standards.
The actual scheduled date for resumption was on March 17. — Bernama