Malaysia
Works minister: Portion of West Coast Expressway project only to be completed within three years due to land acquisition issues
Works Minister Datuk Seri Fadillah Yusof launches a conference for Public Works Department senior officers at a hotel in Ipoh, June 21, 2022. — Picture by Farhan Najib

IPOH, June 21 — A portion of the West Coast Expressway (WCE) project is expected to only be completed in the next three years due to problems faced by appointed contractors as well as land acquisition issues.

Senior Works Minister Datuk Seri Fadillah Yusof said his party was aware of the problems faced and had taken appropriate measures, including changes in the alignment of the project.

Advertising
Advertising

"For the land acquisition process, as we know, it is not under our (ministry’s) control but under the state government. They have had to settle a lot of things, when the land was not ready, the project could not be carried out.

"So I expect a portion of the WCE to only be completed three years from now,” he said after officiating the 2022 Malaysia Public Works Department (JKR) Senior Officials’ Conference (SOC) today.

He pointed out that the contractor faced some technical problems to continue the project in a section of the WCE alignment from Tanjong Karang-Sabak Bernam, Selangor and subsequently, IJM Corporation Bhd (IJM) took over the project.

It had been reported that based on the original schedule, the WCE project was expected to be completed by the end of 2022 or early 2023, but there were some delays due to land acquisition issues as well as new alignments in certain areas. — Bernama

Related Articles

 

You May Also Like