Malaysia
Phase one of Pan Borneo Highway project in Sarawak 71pc complete, says deputy works minister
Contractors carry out construction work on the Pan Borneo Highway near Jalan Mawao Membakut in Membakut January 7, 2020. u00e2u20acu201d Bernama pic

KUALA LUMPUR, Oct 13 — Ten work packages under phase one of the Pan Borneo Highway project from Sematan to Miri have reached 71 per cent completion, as of last September, said Deputy Works Minister Datuk Arthur Joseph Kurup.

He said the Telok Melano to Sematan work package which was also under the same phase of the project was completed in January 2019.

Advertising
Advertising

"Just like other government projects, the Covid-19 pandemic has also impacted the construction work progress of the LPB project in Sarawak which is expected to be completed September 2022.

"As such, various mitigation plans including the realignment of the construction schedule and extension of time (EOT) have been implemented to ensure that construction goes on smoothly,” he said during the question and answer session at the Dewan Negara, here, today.

He was replying to a question from Senator Nuing Jeluing on the status of the construction of the LPB project.

Arthur said the RM16.117 billion worth project which has 11 work packages and commenced in October 2015 involves the construction of a 786km stretch of road from Telok Melano to Miri.

He said the Works Ministry would continuously monitor the progress of the project through regular visits and engagement sessions with the contractors and consultants involved.

"This is to measure the effectiveness of mitigation actions and make improvements to ensure completion of the project,” he said. — Bernama

Related Articles

 

You May Also Like