MRT project slightly ahead of schedule, CEO says (VIDEO)
Malay Mail

KUALA LUMPUR, May 28 — Progress on the highly anticipated MRT project is slightly ahead of schedule, with more than half of its tunnelling works completed, MRT Corp Chief Executive Officer Datuk Azhar Abdul Hamid said today.

“If you look at the progress of the MRT line one overall, as far as our plan is concerned, we are supposed to be at 42.78 per cent completion.

“Actual progress is 43.49, so we are slightly ahead of plan,” he told reporters at the MRT Corp office.

Azhar said that 56 per cent of tunnelling work has been completed, adding that one of the Variable Density Tunnel Boring Machine is working at the most challenging area in the project around Bukit Bintang, where the Karstic Limestone area transitions to the type of underground underfill called the Kenny Hill Formation.


Progress on the highly anticipated MRT project is slightly ahead of schedule, MRT Corp CEO Datuk Azhar Abdul Hamid said today. — Picture by Choo Choy May

So far, three sinkholes have been reported in the Bukit Bintang area, with the one in front of an Audi showroom on Jalan Imbi as wide as 10 metres and 18 metres in length.